California Subcontractor Agreement Template | Statutory Compliant
Generate a construction subcontract tailored to California law — with statutory prompt payment deadlines, retainage caps, lien waiver rules, and anti-indemnification protections built in.
Contract Parties
Subcontractor
Project & Schedule
Payment Terms
Total subcontract price for your scope of work.
California rules: Under Civil Code § 8818, private construction retainage cannot exceed 5% of the contract price.
Days after GC receives owner payment.
Unlock Full Document
Download a clean, print-ready PDF with all California statutory clauses included — prompt payment, retainage, lien waiver, and indemnification.
Live Document Preview
Subcontractor Agreement
Construction Subcontract — State of California
This Subcontractor Agreement (the “Agreement”) is made and entered into as of October 5, 2026 by and between [General Contractor Name] (“General Contractor”) and [Subcontractor Name] (“Subcontractor”), governed by California Civil Code §§ 8000-8822 and the laws of the State of California.
General Contractor
[General Contractor Name]
Subcontractor
[Subcontractor Name]
Project Owner
—
Project Address
—
Contract Price
[Contract Price]
License #
—
1. Scope of Work
Subcontractor shall furnish all labor, tools, equipment, and materials necessary to complete the agreed scope of work in a good and workmanlike manner, in compliance with all applicable building codes.
2. Payment
GC shall pay Subcontractor within 10 days after receiving payment from the Project Owner. Under Civil Code § 8812, the general contractor must pay subcontractors within 7 days after receiving payment from the owner for that sub’s work, plus 1% simple interest per month on late amounts.
3. Retainage
GC may withhold 10% retainage from each progress payment. Under Civil Code § 8818, private construction retainage cannot exceed 5% of the contract price. Retention proceeds must be released within 45 days after the project is completed and a Notice of Completion is filed, minus a 125% withholding for uncompleted work.
4. Lien Waivers
California requires use of the statutory lien waiver forms in Civil Code § 8132-8138 (conditional and unconditional waivers for both progress and final payments). Any non-statutory waiver that fails to meet these form requirements is invalid. A waiver is invalid unless payment was actually received or clearly conditional.
5. Mechanics Lien Rights Preserved
California requires recording a lien within 90 days after completion of the work of improvement (or recording of a Notice of Completion/Cessation, which shortens it to 30/60 days depending on whether the claimant filed a preliminary notice). California requires a preliminary 20-day Notice to the owner, direct contractor, and construction lender within 20 days of first furnishing labor or materials for most claimants other than the direct contractor.
6. Indemnification
Under Civil Code § 2782, construction contract provisions requiring a subcontractor to indemnify the contractor for the contractor’s sole negligence or willful misconduct are void. Type I and II indemnity clauses are permissible; Type III (sole negligence) indemnity is not.
7. Governing Law
This Agreement is governed by the laws of the State of California, including California Civil Code §§ 8000-8822 (California Construction Law, including the Prompt Payment Act at §§ 8800-8815 and Mechanics Lien Law at §§ 8400-8500).
[General Contractor Name] — General Contractor
Print Name / Title
[Subcontractor Name] — Subcontractor
Print Name / Title
This is an on-page preview only. Unlock to download your clean, print-ready PDF.
Secure checkout via Stripe — your form data is saved automatically.
California Payment & Retainage Rules
Under Civil Code § 8812, the general contractor must pay subcontractors within 7 days after receiving payment from the owner for that sub’s work, plus 1% simple interest per month on late amounts.
Retainage Cap
Under Civil Code § 8818, private construction retainage cannot exceed 5% of the contract price. Retention proceeds must be released within 45 days after the project is completed and a Notice of Completion is filed, minus a 125% withholding for uncompleted work.
Pay-When-Paid
Your agreement states that owner payment is a timing mechanism, not an absolute condition precedent — preserving your right to payment and statutory remedies under California Civil Code §§ 8000-8822.
Lien Waivers
California requires use of the statutory lien waiver forms in Civil Code § 8132-8138 (conditional and unconditional waivers for both progress and final payments). Any non-statutory waiver that fails to meet these form requirements is invalid. A waiver is invalid unless payment was actually received or clearly conditional.
Your Mechanics Lien Rights in California
This agreement expressly preserves your right to record a mechanics lien and serve statutory preliminary notices — no pay-if-paid, pay-when-paid, or lien waiver clause in the document can waive your lien rights beyond payment actually received.
California requires recording a lien within 90 days after completion of the work of improvement (or recording of a Notice of Completion/Cessation, which shortens it to 30/60 days depending on whether the claimant filed a preliminary notice).
California requires a preliminary 20-day Notice to the owner, direct contractor, and construction lender within 20 days of first furnishing labor or materials for most claimants other than the direct contractor.
Deadlines matter: missing a California lien or notice deadline can permanently waive your security interest in the project. Calendar both dates the day you mobilize on site.
Indemnification Limits Under California Law
Under Civil Code § 2782, construction contract provisions requiring a subcontractor to indemnify the contractor for the contractor’s sole negligence or willful misconduct are void. Type I and II indemnity clauses are permissible; Type III (sole negligence) indemnity is not.
California Subcontractor Agreement FAQs
When must a general contractor pay me under California prompt payment law?
Under Civil Code § 8812, the general contractor must pay subcontractors within 7 days after receiving payment from the owner for that sub’s work, plus 1% simple interest per month on late amounts. Your subcontract should mirror these statutory deadlines so that late payments automatically trigger the statutory interest and remedies without negotiation.
How much retainage can a GC legally withhold in California?
Under Civil Code § 8818, private construction retainage cannot exceed 5% of the contract price. Retention proceeds must be released within 45 days after the project is completed and a Notice of Completion is filed, minus a 125% withholding for uncompleted work. Your agreement should specify the exact retainage percentage, the release schedule (typically at substantial completion and final completion), and payment of statutory interest on withheld retainage.
Are pay-if-paid clauses enforceable in California subcontracts?
While California has not enacted a blanket statutory ban on pay-if-paid clauses, courts and statutes in most states treat "pay-when-paid" as a reasonable timing provision rather than an absolute condition. Check California Civil Code §§ 8000-8822 (California Construction Law, including the Prompt Payment Act at §§ 8800-8815 and Mechanics Lien Law at §§ 8400-8500) for specific restrictions, and make sure your subcontract states that payment from the owner is not an absolute condition precedent to your right to be paid.
What lien waiver rules apply in California?
California requires use of the statutory lien waiver forms in Civil Code § 8132-8138 (conditional and unconditional waivers for both progress and final payments). Any non-statutory waiver that fails to meet these form requirements is invalid. A waiver is invalid unless payment was actually received or clearly conditional. Never sign an unconditional waiver until payment has actually cleared your bank account, and make sure your waiver identifies the specific billing period and amounts to avoid losing lien rights on future work.
Can a California subcontract require me to indemnify the GC for the GC’s own negligence?
Under Civil Code § 2782, construction contract provisions requiring a subcontractor to indemnify the contractor for the contractor’s sole negligence or willful misconduct are void. Type I and II indemnity clauses are permissible; Type III (sole negligence) indemnity is not. Always read the indemnification clause carefully — even in states with anti-indemnity statutes, "broad form" indemnity for joint negligence is typically still enforceable.
How do I preserve my mechanics lien rights in California?
California requires recording a lien within 90 days after completion of the work of improvement (or recording of a Notice of Completion/Cessation, which shortens it to 30/60 days depending on whether the claimant filed a preliminary notice). California requires a preliminary 20-day Notice to the owner, direct contractor, and construction lender within 20 days of first furnishing labor or materials for most claimants other than the direct contractor. Send statutory notices by certified mail or another trackable method, keep copies of everything, and calendar the deadlines immediately upon each project’s completion.