Contract Parties
Subcontractor
Project & Schedule
Payment Terms
Total subcontract price for your scope of work.
Hawaii rules: Hawaii does not statutory cap retainage on private construction; retainage is a matter of contract negotiation.
Days after GC receives owner payment.
Unlock Full Document
Download a clean, print-ready PDF with all Hawaii statutory clauses included — prompt payment, retainage, lien waiver, and indemnification.
Live Document Preview
Subcontractor Agreement
Construction Subcontract — State of Hawaii
This Subcontractor Agreement (the “Agreement”) is made and entered into as of October 5, 2026 by and between [General Contractor Name] (“General Contractor”) and [Subcontractor Name] (“Subcontractor”), governed by Hawaii Revised Statutes Chapter 444 and Chapter 715 and the laws of the State of Hawaii.
General Contractor
[General Contractor Name]
Subcontractor
[Subcontractor Name]
Project Owner
—
Project Address
—
Contract Price
[Contract Price]
License #
—
1. Scope of Work
Subcontractor shall furnish all labor, tools, equipment, and materials necessary to complete the agreed scope of work in a good and workmanlike manner, in compliance with all applicable building codes.
2. Payment
GC shall pay Subcontractor within 10 days after receiving payment from the Project Owner. Under HRS 444F-3, the general contractor must pay subcontractors within 15 calendar days after receiving payment from the owner. If the owner fails to pay within 30 days of a proper invoice, interest at 1% per month accrues, and the sub may suspend work after 30 days notice.
3. Retainage
GC may withhold 10% retainage from each progress payment. Hawaii does not statutory cap retainage on private construction; retainage is a matter of contract negotiation.
4. Lien Waivers
Hawaii does not require statutory lien waiver forms; waivers are enforceable if they clearly identify the project, amount, and date. Conditional waivers are best practice until payment clears to preserve lien rights under HRS Chapter 715.
5. Mechanics Lien Rights Preserved
Hawaii requires recording a lien within 80 days after the last date labor or materials were furnished. Hawaii does not require a statutory preliminary notice for private construction projects; lien rights attach upon performing work, though a voluntary Notice of Intent to lien is best practice.
6. Indemnification
Hawaii does not have a specific anti-indemnification statute for construction contracts; broad indemnity is generally enforceable if clearly worded. Subcontractors should negotiate express limits and rely on HRS 444F for late-payment remedies.
7. Governing Law
This Agreement is governed by the laws of the State of Hawaii, including Hawaii Revised Statutes Chapter 444 and Chapter 715 (Hawaii Construction Lien Law); Prompt Pay at HRS Chapter 444, Part VIII.
[General Contractor Name] — General Contractor
Print Name / Title
[Subcontractor Name] — Subcontractor
Print Name / Title
This is an on-page preview only. Unlock to download your clean, print-ready PDF.
Secure checkout via Stripe — your form data is saved automatically.
Hawaii Payment & Retainage Rules
Under HRS 444F-3, the general contractor must pay subcontractors within 15 calendar days after receiving payment from the owner. If the owner fails to pay within 30 days of a proper invoice, interest at 1% per month accrues, and the sub may suspend work after 30 days notice.
Retainage Cap
Hawaii does not statutory cap retainage on private construction; retainage is a matter of contract negotiation.
Pay-When-Paid
Your agreement states that owner payment is a timing mechanism, not an absolute condition precedent — preserving your right to payment and statutory remedies under Hawaii Revised Statutes Chapter 444 and Chapter 715.
Lien Waivers
Hawaii does not require statutory lien waiver forms; waivers are enforceable if they clearly identify the project, amount, and date. Conditional waivers are best practice until payment clears to preserve lien rights under HRS Chapter 715.
Your Mechanics Lien Rights in Hawaii
This agreement expressly preserves your right to record a mechanics lien and serve statutory preliminary notices — no pay-if-paid, pay-when-paid, or lien waiver clause in the document can waive your lien rights beyond payment actually received.
Hawaii requires recording a lien within 80 days after the last date labor or materials were furnished.
Hawaii does not require a statutory preliminary notice for private construction projects; lien rights attach upon performing work, though a voluntary Notice of Intent to lien is best practice.
Deadlines matter: missing a Hawaii lien or notice deadline can permanently waive your security interest in the project. Calendar both dates the day you mobilize on site.
Indemnification Limits Under Hawaii Law
Hawaii does not have a specific anti-indemnification statute for construction contracts; broad indemnity is generally enforceable if clearly worded. Subcontractors should negotiate express limits and rely on HRS 444F for late-payment remedies.
Hawaii Subcontractor Agreement FAQs
When must a general contractor pay me under Hawaii prompt payment law?
Under HRS 444F-3, the general contractor must pay subcontractors within 15 calendar days after receiving payment from the owner. If the owner fails to pay within 30 days of a proper invoice, interest at 1% per month accrues, and the sub may suspend work after 30 days notice. Your subcontract should mirror these statutory deadlines so that late payments automatically trigger the statutory interest and remedies without negotiation.
How much retainage can a GC legally withhold in Hawaii?
Hawaii does not statutory cap retainage on private construction; retainage is a matter of contract negotiation. Your agreement should specify the exact retainage percentage, the release schedule (typically at substantial completion and final completion), and payment of statutory interest on withheld retainage.
Are pay-if-paid clauses enforceable in Hawaii subcontracts?
While Hawaii has not enacted a blanket statutory ban on pay-if-paid clauses, courts and statutes in most states treat "pay-when-paid" as a reasonable timing provision rather than an absolute condition. Check Hawaii Revised Statutes Chapter 444 and Chapter 715 (Hawaii Construction Lien Law); Prompt Pay at HRS Chapter 444, Part VIII for specific restrictions, and make sure your subcontract states that payment from the owner is not an absolute condition precedent to your right to be paid.
What lien waiver rules apply in Hawaii?
Hawaii does not require statutory lien waiver forms; waivers are enforceable if they clearly identify the project, amount, and date. Conditional waivers are best practice until payment clears to preserve lien rights under HRS Chapter 715. Never sign an unconditional waiver until payment has actually cleared your bank account, and make sure your waiver identifies the specific billing period and amounts to avoid losing lien rights on future work.
Can a Hawaii subcontract require me to indemnify the GC for the GC’s own negligence?
Hawaii does not have a specific anti-indemnification statute for construction contracts; broad indemnity is generally enforceable if clearly worded. Subcontractors should negotiate express limits and rely on HRS 444F for late-payment remedies. Always read the indemnification clause carefully — even in states with anti-indemnity statutes, "broad form" indemnity for joint negligence is typically still enforceable.
How do I preserve my mechanics lien rights in Hawaii?
Hawaii requires recording a lien within 80 days after the last date labor or materials were furnished. Hawaii does not require a statutory preliminary notice for private construction projects; lien rights attach upon performing work, though a voluntary Notice of Intent to lien is best practice. Send statutory notices by certified mail or another trackable method, keep copies of everything, and calendar the deadlines immediately upon each project’s completion.